i have a ressource affected on 2 project. 100% on project A and 100% on project B.
On the planning by ressource, ressource work on project B during 3 days, then on project A during 10 days, then on project B during 3 days. It's ok, but on planning view the green line for project B is continue. Is it possible to draw a discontinued line when ressource don't work on a project ?
Is it possible to draw a discontinued line when ressource don't work on a project ?
No, it's not.
Gantt planning is based on JsGantt library, that only deals with start and end dates.
The library has been extended to also take into accound real start and real end dates, in completion to planned start and planned end dates.
So there may be 2 lines : one grey for real, one green (or red) for planned.
There is no simple way to split lines corresponding on work, day by day.
Today, planning display is yet very time consuming, and provides poor performance when displaying many lines (many activities). So there is no planned evolution in a way that could degrade performance still more.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.