Milestone S Curve

More
21 Mar 2017 14:17 - 21 Mar 2017 14:18 #1 by Iaurkano
Milestone S Curve was created by Iaurkano
Hi every body, and especially Babynus,

We would like to show an S Curve indicator, but only for project milestones.

Should it be possible to have option in this reports to show S Curve for activity only , activity and milestone (like it's done today, if i'm right) or milestone only.

we have 45° curve for milestone, it should be great to have the same for S Curve.

Thank's a lot, and a big thank's for your job.
Last edit: 21 Mar 2017 14:18 by Iaurkano.

Please Log in or Create an account to join the conversation.

More
22 Mar 2017 16:19 - 22 Mar 2017 16:19 #2 by babynus
Replied by babynus on topic Milestone S Curve

S Curve indicator, but only for project milestones

I really don't understand what you try to get.
S-Curve is a work beased curve (progress on how work will be used).
And milestones have no work....
So for me S-Curve on Milstones means nothing.

Babynus
Administrator of ProjeQtOr web site
Last edit: 22 Mar 2017 16:19 by babynus.

Please Log in or Create an account to join the conversation.

More
24 Mar 2017 14:01 #3 by Iaurkano
Replied by Iaurkano on topic Milestone S Curve
I babynus,

i would like to get milestone progress. In fact for a project wich contains lot of sub-project there are lot's of milestone, milestone which could have the same name, for example.

the 45° curve is not usable when you have more than 10 milestone.

So, I would like to see milestone progress Using the S Curve indicator, bases not on work, but on mile stone status.

at the begining of the projet mile have validated date, you could used these date in a recorded planing, and compare this with the real milestone status and date.

is it clear .... The main différence of activity S Curve is that the weight of each milestone is the identical, it's not the case for work.

Please Log in or Create an account to join the conversation.

More
25 Mar 2017 16:56 #4 by babynus
Replied by babynus on topic Milestone S Curve
I still don't agree with you : S-curve cannot be used for milestones.

S-Curve shows how work is done (or palnned to be done), day by day.
As milstones have no work, S-Curve for milesotnes means nothing.

I guess what you request is similar to "remaining activities" in "burndown chart" but for milestones and the other way round ("done milstones")
Is that it ?

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
27 Mar 2017 08:58 #5 by Iaurkano
Replied by Iaurkano on topic Milestone S Curve
Ok,

I understand what you mean. In fact, your right, the need is similar to "Burndown chart", but not for activity but fot milestone.

Why, i talked about S Curve, it's because the milestone validation progression as a fonction of time looks like an S Curve, that's all.

The need is to anticipate time lag by analyzing milestone progress.

Thank's for everythings.

Please Log in or Create an account to join the conversation.

More
27 Mar 2017 09:07 #6 by babynus
Replied by babynus on topic Milestone S Curve
Request recorded as Ticket #2617

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.036 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.