I'm using V.8.0.4.
As is shown in the next picture, the resource is working full time on project 4.2 (priority 500) from September.
And the resource is doing nothing on project 9.2 (priority 400) the last week of August but half time on project 4.2.
How should I do so that the resource works on project 9.2 and finish it in August and start full time on project 4.2 despite the fact that the resource is allocated from 1/9? You see that the priority on the project doesn't seem to work.
hi
your resource works in full time on this activity before september ?!
Nevertheless, if you want that your resource work on one project ( and its activities) and not another one, you can either play with priorities, or periods of allocation, or dependencies, or milestsones, or planification mode like " not start before validated start date " for the activitry which follows this one. In fact, your resource works on others activities without ending another one, it is just because " you play" with all this features. I can t find easily what you have done wtih just the few informations you get to us.
The software never goes wrong
Regards.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.