Assigned work is displayed by resource. it shows the total of days (or hours) of work on the whole activity, it means that is not divided by weeks displayed.
What is the matter with decimal number ? On displays you are already working with decimals!?
Have you don't reevaluated the left work at one time or another to get a decimal ?
Then I have a problem. The assigned work shows in the first image doesn't match the assigned work on the activity. The first activity has assigned 56 hours to the resource.
No, the person is only assigned by integer hours no digits. I haven't done any evaluation, just created the project and did planning. No real work has entered.
I guess your unit for work is days (display of planned work shows 1 for a full day).
So you define work in hours, and enter work in days (the most weird situation)
You may change this on global parameters.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.