I asked my team to submit and validate weeks as soon as the week is finished.
But we encountered a problem : Some tickets take more than 1 or 2 weeks to be finished and when a week is validated it become impossible to add consumed time on these tickets in newt weeks.
Is this by design or did we miss a parameter to tune?
In case it is by design do you have any suggestion
Thanks in advance

Please Log in or Create an account to join the conversation.

More
24 Jun 2019 15:57 #2 by babynus
You can enter work on day other than current day with button "dispatch work"