Hello
We have problems with "Stains" Activities and only with certain users. (especially with new users), they don't appear in the 'Agenda' module, but they do appear well in the 'Planning'.
we created "Stains" Activity with an X Manager and assigned User X with a time of 7H on that spots.
We rotate the system so that the activity appears in the Calendar, but it doesn't work. (By zooming in on activity, nothing appears in the "Planned Date" area)
We do the same actions, with the same dates and with a User Y that exists for a long time is there, it works.
Since this Activity appeared, we tried to put User X in charge and assigned it, we ran the system and the activity disappeared from the Schedule and the "Planned Date" disappeared on the activity!
it was deduced that this may have come from the creation of the user!
So we created a Z User using the copy icon that is on user Y that works. We recreate an Activity in pheasants the same actions, but it does not work!
We do not see where is the problem, do you have a solution?
Chjeck capacity of resource.
Possibly capacity is set to zero.
It was an issue (that has been fixed now) that defaut capacity was set to 0 instead of 1.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.