If could be possible, if assigned work is not defined...I was wondering if that is possible to adapt the calculation of the remaining working time to this:
validated work - real work = remaining work (with the percentage progress bar based on the result)
No, Left is always Assigned - Real (if left is not redefined).Today, the remaining time is calculated between multiple values (validated work, real work, assigned, reassessed).
Please Log in or Create an account to join the conversation.
Please Log in or Create an account to join the conversation.
Please Log in or Create an account to join the conversation.
Please Log in or Create an account to join the conversation.
No, adding "everyone" may be an unexpected feature. Pool is not project dependent, so it would add all resources of the DB, and it could be a real mess for instances with hundreds of resources... or we should add mass removal.I need to repeat the operation of allocation multiple times to include everyone in the pool. Possible to add that functionality you think ?
Please Log in or Create an account to join the conversation.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.