You do not give any workload on this activity, you have just given a duration of 5 days; it is normal that the planning does not change. Please read the friendly manual to undestand how works Projeqtor and especially on various planification modes.
Have you assigned resources on activities with woarkload before ?
On time sheet :
Entering real work ( as planned) you are going to modify the % of progress.
Entering real work ( not as planned ) you are going to modify the % of progress and influence the next planification.
Entering a new left work you are going to modify the % progress and influence the next planification
Projeqtor always calculates plannings considering what has be done and what should be done at any present time to get the better view of the futur.
Or possibly you can define your activities with planning mode "fix duration", so that calculation knows whatr you want to do.
If you left default planning mode "as soon as possible", prpojeqtor expects some assiogned work to correctly plan the tasks.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.