Hello,
After updating to the last version, and calculating activities planning, activity date has become abnormal. Am i missing something?
As a note: i have used pool resource, assigned it to avtivities and also used "unique resource" option in another project.
Hello again,
I spotted that the problem might be related to "not splitted work", because when i disabled that option of an activity, its planned date has become reasonable.
It you set "not splited work" and set limit to 1 (full time), it resource has some regular work, even for 0,1 day about once a week, the task will be postponed until a time frame is found where the resource can work 100% on the task without any (aven small) interuption.
Remove the constraint or lower the threshold so that calculation can consider that enven not full day is stil "not splitted"
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.