03 Apr 2020 14:54 #1 by lansing57
Hello,
First of all I want to congratulate you for this software. i can image the effort behind it.

My question is maybe simple. in the Gantt display, the critical path calculation seems not working when it passes through a milestone who is floating in planning.
When it's a fixed milestone, then it works.

is there a trick?
Best regards,

Please Log in or Create an account to join the conversation.

More
06 Apr 2020 10:21 - 06 Apr 2020 10:21 #2 by babynus
Replied by babynus on topic Critical path calculation
Hi,

I cannot reproduce.
Simple test works as expected

Can you please give exemple, or best propose use case in Demo instance (demo.projeqtor.org)

Babynus
Administrator of ProjeQtOr web site
Attachments:
Last edit: 06 Apr 2020 10:21 by babynus.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.063 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.