How FTE variation works?

More
14 May 2020 11:33 #7 by rakoun
Replied by rakoun on topic How FTE variation works?

alainforma wrote: Hello

Please , post on the forum directly to make it easier for our community

?, what do you mean. It is not the forum here?

Regards,

Please Log in or Create an account to join the conversation.

More
14 May 2020 11:59 #8 by babynus
Replied by babynus on topic How FTE variation works?
Import images in the forum, and add image in the message, instead of posting links to your dropbox

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
14 May 2020 15:11 #9 by rakoun
Replied by rakoun on topic How FTE variation works?
Ok, my post as you want it is.

rakoun wrote: Hum...

Perhaps I did not understand.

Below my configuration with standard FTE of 1 and no variation:



And below a task in my planning with this configuration (task duration is 8h):


Now I change my FTE configuration inserting a period of variation with a FTE of 0.5 and keep a standard FTE of 1. (the example task is in the period and begin 15 june)


this is the result on my planning?


I expected that Projeqtor will put the task on two days and not only one day.

What is wrong?

Regards,

Please Log in or Create an account to join the conversation.

More
15 May 2020 08:57 #10 by alainforma
Replied by alainforma on topic How FTE variation works?
Hi,

it should be, but not necessarily with 0,5 each day ( it is a maximum allowed to be planifed on one or more activities per day)
first, have you recalculated the planning ? i think so.
Secondly, is this resource planned among others projects ?

You can make a right click over the bar in order to watch how the work is planned
The following user(s) said Thank You: tblanken

Please Log in or Create an account to join the conversation.

More
15 May 2020 17:36 #11 by rakoun
Replied by rakoun on topic How FTE variation works?
Hello,

It is weird.
Yesterday after all my changes in ETP configuration I recalculated the planning.
Today I recalculated the planning again and I got the following:


So I returned in ETP configuration then removed ETP variation configuration.
I recalculted the planning but unfortunetaly it does not change??

Are there a cron that is launched during night and that is needed by ETP configuration to be OK?

Regards,
Attachments:

Please Log in or Create an account to join the conversation.

More
18 May 2020 15:21 #12 by rakoun
Replied by rakoun on topic How FTE variation works?

rakoun wrote: Hello,

It is weird.
Yesterday after all my changes in ETP configuration I recalculated the planning.
Today I recalculated the planning again and I got the following:



So I returned in ETP configuration then removed ETP variation configuration.
I recalculted the planning but unfortunetaly it does not change??

Are there a cron that is launched during night and that is needed by ETP configuration to be OK?

Regards,


Hello,

Any idea, I thinks we are on the verge to close this issue.

Regards,

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.091 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.