28 Apr 2020 15:59 #1 by fmt
From my experience, I understand that meetings are taken into account in Gantt, until they are in "closed" status.
My questions :
- Can we disable displaying meetings in Gantt ?
- Where is configured the condition of displaying meetings in Gantt (i.e. displayed until closed ?)

Thanks,

Regards

Please Log in or Create an account to join the conversation.

More
28 Apr 2020 19:41 #2 by babynus

- Can we disable displaying meetings in Gantt ?

No
But you can put then under a dedicated activity and "collapse" the activity so that you'll have only one line.

- Where is configured the condition of displaying meetings in Gantt (i.e. displayed until closed ?)

Nowhere.
It is default behavior, also applied to activities and milestines : they are always visible until closed.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.