Set an indicator to alert internal after the planned end date.

More
03 May 2020 09:58 #1 by iconic
Is there a way to Set an indicator to display or mail a reminder or alert after a specific number of days past the planned end date.

At the moment the indicator function only allows you to set reminders and alerts before the end date. I am trying to find a way to get our project leaders to check specific activities that may be overdue or late.

Is this possible?

Please Log in or Create an account to join the conversation.

More
04 May 2020 08:50 #2 by babynus
No, you cannot through indicators.
But possibly youj can try with Notifications.
This system is a bit "technical", but very powerfull.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
04 May 2020 09:10 #3 by iconic
I have read the manual on notifications and I do understand it. Can you provide detailed steps of how I can do what I need with Notifications.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.