Using a CSV import template, I uploaded yesterday activies, some of them contains Start/End Planned/Validated Dates. Finally everything has been recorded with 09/05/2020.... This morning I updated dates into each corresponding activities but it didn't udpate the planning view.
Attached the Template in xlsx.
Could you help and explain me what is going on? Where did I do errors?
After importing activities, you must go to Planning view and execute planning calculation (gear button)
Planned dates are not imported as they will be calculated by the tool.
Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: Julien Gahon
Set planning mode "do not start before validated start date", enter expected start date as validated start date (not planned start date that won't be imported and systematically changed by planning calculation) and import activities in the order of start date so that they have WBS in same order.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.