[SOLVED] Planification Mode

More
11 Jun 2020 10:23 #1 by Julien Gahon
Hi,
Yesterday I uploaded and calculated my 1st planning inti ProjeQtor, by putting "Mode de planification" 1 into the Activity mass import tempate.
Then It calculated it by ordering activities next to the order following WBS breakdown (end dates) and not the start dates.

How can I arrange that?

What it the parameter or the function that manages it.

thanks & regards,
The topic has been locked.
More
11 Jun 2020 16:57 #2 by Julien Gahon
Replied by Julien Gahon on topic Planification Mode
I solved my issue by marking activities out of the planning calculation.
The topic has been locked.
More
11 Jun 2020 17:28 #3 by babynus
Replied by babynus on topic Planification Mode
Hi,

Projeqtor calculates a Capacity planning and does not take care of Start Date, unles you use planning mode "not start before validated start date" or "regular between dates".
And to order planning, it uses dependencies and priorities of activities. Defaut activity priority is WBS order. That can explain the result you get.
Just order tasks in the WBS the same order you want them to be treated to get what you expect.

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.