Hi,
Yesterday I uploaded and calculated my 1st planning inti ProjeQtor, by putting "Mode de planification" 1 into the Activity mass import tempate.
Then It calculated it by ordering activities next to the order following WBS breakdown (end dates) and not the start dates.
How can I arrange that?
What it the parameter or the function that manages it.
Projeqtor calculates a Capacity planning and does not take care of Start Date, unles you use planning mode "not start before validated start date" or "regular between dates".
And to order planning, it uses dependencies and priorities of activities. Defaut activity priority is WBS order. That can explain the result you get.
Just order tasks in the WBS the same order you want them to be treated to get what you expect.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.