10 Jul 2020 08:02 #1 by service.automation
Hi,

I'm facing the following.

I'm assigned to a task, but I can't feel my timesheet related to this task.

What should be wrong in my configuration ?

Many thnaks for your support,

Fred
Attachments:
The topic has been locked.
More
10 Jul 2020 10:19 #2 by Gautier
Hello,

I think you have in global parameter, section timesheet , parameter : display only handled tasks : YES.
That is why you can display only handled task. If you want see your activity, you have to change statuts of your activity to get handled checked.
Maybe change your status to assigned to in progress.
The topic has been locked.
More
10 Jul 2020 12:33 #3 by service.automation
Hi,

Correct !

Many thanks,

Fred