Hi,
For specific reason I need that people be surbooked without any impact on planning calculation. That he may do for example 16 hours/day. How can I manage that? I remember it might be somewhere something like an "allow surbooking or overcapacity" parameter to select.
in resource, enter capacity variation : resource will be planned up to new capacity, and will have to enter work up to new capacity
in resource, enter overbooking period : resource will be planned up to new capacity (capcxity + overbooking), and will have to enter only standard capacity
in planning calculation, check "Plan with overuse (infinite overbooking capacity)". No change on resource, will be considered with no capacity limit, and be able to manage several tasks on same time (will generate over use)
(this must be anable through specific access right)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.