i don't manage to use properly the report "plan of charge per ressource - monthly" (sorry for the bad translation..). I want to exploite the possibility to see planned time. So i have made this test :
Create an activity and refresh the planning :
Consult the report :
there is no time for a planned work in September.. I must be mistaken but i can't find where.. thanks for your help
In the screenshots you provide, I don't see real work or planned work, but only validated work.
I remind you that the dates indicated for the validated work are only informative and do not take into account in the calculation of the charges except in some very specific planning modes.
Except the report that you want to view only shows planned or real work. The real being the priority.
If no work is entered in the planned work, it is probably because you did not recalculate the planning.
Click on the calculation button or check the automatic calculation box so as not to forget to recalculate when you are on this page.
And finally, if the planning mode you have chosen is the "as soon as possible" mode then there is a good chance that the 2 days of charges that you have entered will be planned in August. The "handled" checkbox is dated August 19, this gives a little clue.
After recalculating, check the planning for this resource by right-clicking directly on the activity bar. You will then see where these two days have been positioned.
i found the problem why the planned work wasn't displayed. The ressource was booked with too many activities at a rate of 100% so it wasn't possible to planned anything.
As there is no specific warning, it's difficult to find the origin of the mistake when a ressource is working on lots of projects at the same time. On the right clic on the taks in the planning, something like "work impossible to plan, the ressource is overbooked" could be useful.
Yes of course your resource can not be planned everywhere on all activities per day at the same time.
Be careful ! The rate you talk about do not react into projeqtor calculation on resource's planning as you explain.You are wrong on what you have written.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.