I have a resource that does a certain activity (Activity X) every day, let's say it is for an time a 0.1 day
When this person goes into her time-sheet to input the time spend on various activities during a week, is there a way that in time-sheet the time spent on activity X is automatically filled with 0.1 every day, so she just has to input the time spent on her other activities ?
Hello
NO but :
Just one way :
Manual planification mode with the global parameter set up as "planificated manual date are workload done in the futur" ( since V 8.5.)
I tried your solution.
It works using Manual amplification mode except that the minimum amount of work I can manually specify for a given day is 0.5 and I what I need is to specify 0.1 for each day of the week. I worked around it specifying 0.5 every friday
Now when my resource access her time-sheet 0.5 are already inputted every friday and she can change it if she wants : not exactly what I needed but close enough
I use version 8.5.4 but I couldn't find in the global parameter the parameter you were talking about : ""planificated manual date are workload done in the futur" : where is this parameter exactly ????
instead I used "manual planned interventions enter work as " and set it to real
You are right, you can only plan by half day with manual planification.
This parameter can be reach only from V8. 5 on global parameter : work :planning 6th line.
Have you ever tried to use "recurent" mode on planification mode, so you can plan 0,1 per day easily.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.