25 Aug 2020 01:41 #1 by codecanvas
Hi,
I came across ProjeQtOr and currently evaluating it. So far I love the functionality the application provides, great work!

I would like to know if we can keep the WBS specific to the project. For example if I have 3 projects for 3 different clients, I don't want the 2nd and 3rd clients WBS number to start with 2.x and 3.x. Since each will have their own set of WBS, I think it makes sense to keep WBS numbering compartmentalised to each project. It would be great if we have an option to always start each project's WBS with 1.x...

If there is already an option to do this, then kindly point me to the correct settings. I searched but was not able to find any settings for the same.

Thank you!
The topic has been locked.
More
25 Aug 2020 18:39 #2 by babynus
This is not possible.
Numbering is always absolute. You cannot get a "relative WBS".
NB : WBS must be unique, so you cannot have several levels starting with 1.

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.029 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.