ProjeQtOr free project management software - [SOLVED] Activity Postponed - ProjeQtOr
 
 

[SOLVED] Activity Postponed

More
11 Sep 2020 15:45 #1 by service.automation
Hi,

I'm facing the following.

The activity was shedulled to start on 07/09/20.

The responsable of activty, handled the task the exact day when the task started on 07/09/20.

But the task is every day posponed (In this case on 11/09/20)......And the other task sheduled are also postponed.....

The planned date is postponed each day.

I don't understand this stituation..

Any idea too fix it ?

They are a link with reel time.....in Timesheet ?

Thanks

Fred
Attachments:

Please Log in or Create an account to join the conversation.

More
11 Sep 2020 16:14 #2 by babynus
Replied by babynus on topic Activity Postponed
There is some left work (80 hours).
So Activity is not done...
Postponing it is normal.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.