Predecessor End-Start is not taken into account in the planning calculation

More
15 Sep 2020 14:59 #1 by ridjy
Hi,
Thanks for this incredible software,

I'm using the planning calculation and I want to know
In which case the end-of-start predecessor is not taken into account in the planning calculation?

When i create the dependency to end-start the two tasks are planned one after the other.
For the 2 tasks : each one assigned to a different resource
Run planning again : tasks are planned in parallel.

Thanks,

Please Log in or Create an account to join the conversation.

More
18 Sep 2020 15:12 #2 by babynus
Hi,

Dependencies are not taken into account :
- when successor is already started (real start date is set)
- when tasks has somle "fix" mode : regular between dates or manual planning

But it seems there is an issue is some case on V8.5.5
We are investigating.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: ridjy

Please Log in or Create an account to join the conversation.