I'm using the planning calculation and I want to know In which case the end-of-start predecessor is not taken into account in the planning calculation?
When i create the dependency to end-start the two tasks are planned one after the other.
For the 2 tasks : each one assigned to a different resource
Run planning again : tasks are planned in parallel.
Dependencies are not taken into account :
- when successor is already started (real start date is set)
- when tasks has somle "fix" mode : regular between dates or manual planning
But it seems there is an issue is some case on V8.5.5
We are investigating.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.