Hello there,
I am using version 8.5.5 of the Projeqtor and added a few Activity->Task under a Project. I later linked them. I saw that the Gantt Chart was not aligned properly. I used the Calculate Capacity Planning button and saw that it did not change anything. The Gantt Chart did not update.
I tried the same thing with version 8.6.0 and it still has the bug.
I also tried deleting the links and reconnecting them, still it did not work. All the tasks are aligned from the start date. Also what does Validate planning mean. I tried that button and feel that caused the entire issue.
Hope you will fix the basic thing needed for the software to work quickly.
By default, ProjeQtOr calculates a capacity planning.
This means that unless you set planning mode as "fixed duration", you need to assign some work to get a planning calculation.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.