01 Dec 2020 10:59 #1 by bgenolini
Hello,
I need your help on the following issue:
A project member -call him Luke- leaves a project on Dec. 31 this year. He will be replaced by Rey, who is already working on the project, with a working load compatible with this replacement.
I have tried the replacement button on a dummy project, specifying that the "new" Rey starts working on January 1st, 2021. Luke is affected until the end of the year, but Rey also! Is there a means to force her affectation on Luke's tasks after Dec. 31st, while keeping her previous affectations? I would not like to modify all the tasks in the existing project.

Thanks in advance.

Bernard

Please Log in or Create an account to join the conversation.

More
01 Dec 2020 11:39 #2 by alainforma
Hi
Do not worry, the assignments will be changed automatically without having to change them manually. Please note that on project screen you will get two lines for the remaining resource on allocations that you are allowed to change anyway

You re welcome.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.