[SOLVED] Automatism on imputation

More
17 Dec 2020 08:27 #1 by Yannobi
Hi,

After 7 days of work, all activities planned by projeqtor (hours affected to an activity for a day) are automatically validated as real work if the technician did not entered some real work.

How and where do i change this automatism ?

Thank you

Please Log in or Create an account to join the conversation.

More
17 Dec 2020 09:46 #2 by alainforma
Replied by alainforma on topic Automatism on imputation
HI

Global parameter / automation / generation of alerts

Please Log in or Create an account to join the conversation.

More
17 Dec 2020 09:57 #3 by Yannobi
Replied by Yannobi on topic Automatism on imputation
I found it :

Global parameter / automation / automatic planning calcul /

At the end of the section : "Alimentation automatique du réel :" Non

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.