[SOLVED] Activities -- Incorrect Left Work

More
02 Mar 2021 14:46 #1 by karl.binet
Hi, 
V9.0.2
in an activity the left work value is incorrect, 
Assigned work is : 409.75
Real work is : 368.25
Left work shoud be : 41.5 but the value is at 355.75

 

i've tried "scan for issue and fix issue" did not solved the issue.

Anything else i can do to fix this issue

for now i have manually changed the value but i really don't know if its a good thing to do

thanks for you help

regards
Attachments:

Please Log in or Create an account to join the conversation.

More
03 Mar 2021 11:31 #2 by Flou
Hello,

have you changed the assigned work with a higher value?
the only solution to change this when it happens is to change the rest manually like you did.
The following user(s) said Thank You: karl.binet

Please Log in or Create an account to join the conversation.

More
03 Mar 2021 13:48 #3 by karl.binet
Hello, i can't tell if someone change the assigned work, but thanks for your reply i will change manually the rest value if it happens again.

Regards

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.044 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.