Hello,
All resource allocations are being handled by Projeqtor, therefore if there are already tasks during the same period of a resource, they may be trimmed by the Projeqtor and the new ones are replaced into the trimmed areas. In reality, no one repeatedly works just an hour in a week for an activity of a project.
Can it be a constraint of Projeqtor's algorithm that attempts to make the activity finish according to "as soon as possible" rule?
Yes, it is possible that this is the "as soon as possible" planning mode causing the resource to be planned like this. There is the allocation of the resource to the project, the capacity and calendar of the resource which can contribute to this result.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.