09 Jun 2021 08:41 #1 by bvd
HI,

We would like to use projeqtor without timesheets and imputations and then, pilot our projects by task completion.

However, we plan to keep capacity planning :-)

Is it possible ?

I dont find the option to disable timesheets and imputations.

Regards,

Please Log in or Create an account to join the conversation.

More
09 Jun 2021 12:34 #2 by Flou
Hello,

want to do some planning without having real work on the project?

For disable timesheets go on module management and disable module Time tracking.

Please Log in or Create an account to join the conversation.

More
12 Jun 2021 18:06 #3 by babynus
Capacity planning without timesheets and input of real work ... is not capacity planning (in my opinion)

What you try to do is possible :
 - on global parameters, activate "manual progress of fixed duration activities"
 - then set all tasks to "fix duration" planning mode (you can set activity types to this mode so that all new ones will use it)
You'll then get a manual input of tasks.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
13 Jun 2021 15:47 #4 by bvd
Thank you for your reply.

Capacity planning is used to plan .... capacity :-). For us, it has nothing to do with tracking time spent on tasks.

In our case, we don't need to follow the real work. We use projeqtor to plan activities and projects that are executed by providers.

We also use it to manage projects by quality (risks, actions, decisions, questions and problems).

I will give a try with your suggestions.

Regards

Please Log in or Create an account to join the conversation.

More
15 Jun 2021 11:15 #5 by babynus

Capacity planning is used to plan .... capacity. For us, it has nothing to do with tracking time spent on tasks.

Tracking real work done is mandatory for capacity planning.
Moreover, tracking left work, that may be different from assigned - real is the key to anticipation.

In our case, we don't need to follow the real work. We use projeqtor to plan activities and projects that are executed by providers.

Then manual progress should fit your needs as it was designed for this purpose.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.036 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.