dates in projeqtor tool

More
29 Jul 2021 10:34 #1 by jagriti.pandey
There are so many dates in projeqtor.
could u please explain following dates with good example 
start date
done date
creation date
validated start date
validated end date
real start date
real end date
requested end date
requested start date
planned start date
planned due date



 

Please Log in or Create an account to join the conversation.

More
30 Jul 2021 11:36 #2 by babynus
Replied by babynus on topic dates in projeqtor tool
Have a look at the beautiful user manual that in provided with the application and directly reachable through F1 with contextual access.
Or in other word : RTFM

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
30 Jul 2021 12:11 - 30 Jul 2021 12:12 #3 by jagriti.pandey
I initially read user manual for dates but In the user manual, dates are not explained clearly. could you please explain again here with good example.

Already messed up with so many dates.

what is difference b/w start date vs validated start date vs planned start date??
Similarly diff b/w planned due date vs planned end date or done date ??
Last edit: 30 Jul 2021 12:12 by jagriti.pandey.

Please Log in or Create an account to join the conversation.

More
30 Jul 2021 12:43 #4 by Arkhanje
Replied by Arkhanje on topic dates in projeqtor tool
It is true that one or two details are missing from the manual and the next version will be a little more explicit thanks to you.

To keep it short and simple:

Requested: customer's request
no impact on planning EXCEPT if it is the one and only constraint entered.

Validated: What you plan
Used for certain planning modes and to compare the drifts with the dates planned by the software

Planned: What the software calculates for you
You do not have direct control over these dates. The calculation takes into account absolutely all your constraints to calculate a planning with total care.

Real: What you achieve
You fill in the real work on your timesheet. It's done.


The creation date is the date you create the item
The in progress date is when you start to work on the element.
The end date is when you're done, no more left work to do.
The closing date is when you close your item.
The modification date is the last date on which the item was modified.


I don't think we can be any clearer.
Now if you have a hard time with writing, we have great training. Do not hesitate to request a quote with our contact form.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.037 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.