No; allocaton to Organization is unique for each resource.
But as Projects Structure is open (you can have several levels of projects / sub-projects) you can use project object to describe the organizations and then allocate resource to several projects that describe organizations.
Thank you for your reply.
As a french user i m not sure to totally understand your reply.
Basically my problem is that i want to affect projects to organisation. But ressources that input real work (timesheet) are not associated to one or another organisation. So, when i want to use reports, there is no data.
To do what you expect, just create new Project "Organization A". It's not a real project, but you can move your projects of this organization under this parent project (as sub-projects).
Then on reports, just select the project "Oraganization A" to have data for all the projects (whatever the resources)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.