Intervention modality can not be setted after imputation is done ?

More
02 Mar 2022 17:46 #1 by milien56
Hello,

I want to track homeworking, independantly from activities performed.
It sounds that "Planned intervention" feature with 'Intervention Modality" can be used for that.
However it's impossible to set an intervention modality if available workload for a ressource is null. (imputation on activities already done for this day).
I got an error message "unsufficiant workload for this ressource".
Am i using the feature the right way ?

Thanks
Br

Please Log in or Create an account to join the conversation.

More
03 Mar 2022 00:06 #2 by babynus
No, it's right.
Defaut behavior block entering Planned Intervention (that books planned work or real work) that would additionnaly to existing real work be more than resource capacity.
But you can change this behavior with parameter on Global Parameter > Planning > effect of capacity on planned interventions : select none...

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
03 Mar 2022 16:37 #3 by milien56

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.030 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.