ProjeQtOr free project management software - [SOLVED] How/When does Real Start Date & End Date updates in Planning->Activity->Progress - ProjeQtOr
 

[SOLVED] How/When does Real Start Date & End Date updates in Planning->Activity->Progress

More
15 Mar 2022 08:07 #1 by chandrashekhar
Hi,

I tried my way to check How / When Real Start & End Date updates in Planning->activity->progress section, but I didn't find a way.
Please help me to understand that part.
Attachments:

Please Log in or Create an account to join the conversation.

More
15 Mar 2022 08:57 #2 by babynus
Real dates are set when you enter real work on Timesheet.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: chandrashekhar

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.