I find using Resource Pools is a great feature for planning in advance
Is it also possible to use Pools for reporting real work ?
I was hoping for example to use the "work for a resource - monthly" report to get all work done by the resources of a Pool.
Is that possible ? (maybe using a different configuration than what I tried)
No, selection for resource on work reports cannot be a pool as real work is not entered on the pool but on the real resources.
You must use report "work - monthly" then apply a filter on resources : the only available are Oraganization and Team.
So maybe if you can have Team fit the Pool, you win.
Otherwise, this report shoud need improvment with filter for resources on "Pool" (which does not exist yet)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.