[SOLVED] Real work reports with Resource Pools

More
31 Mar 2022 15:22 #1 by caccia
Hi,

I find using Resource Pools is a great feature for planning in advance :)
Is it also possible to use Pools for reporting real work ?

I was hoping for example to use the "work for a resource - monthly" report to get all work done by the resources of a Pool. 
Is that possible ? (maybe using a different configuration than what I tried)

Thanks

Please Log in or Create an account to join the conversation.

More
31 Mar 2022 15:56 #2 by babynus
No, selection for resource on work reports cannot be a pool as real work is not entered on the pool but on the real resources.
You must use report "work - monthly" then apply a filter on resources : the only available are Oraganization and Team.
So maybe if you can have Team fit the Pool, you win.
Otherwise, this report shoud need improvment with filter for resources on "Pool" (which does not exist yet)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
31 Mar 2022 16:02 #3 by caccia
OK, that's clear in any case - thanks for the answer.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.038 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.