As is showing alert message by Projeqtor, I tried with extending validated date , but message is yet showing ! & I can't find Warning Threshold date (where it is mentioned?). Please guide how to manage?
Value is in "Indicators" or "indicators per project".
An alert that has been generated will show until you "close" it, even if value that triggered it came back to normal.
Warining value is calculated from indicator definition.
If you define indicator on Activity for Validated end date (your example) with warning value at 1 open day, warning value for the activiy is calculated as 1 open day before validated end date.
For instance if validated end date is 2022-04-12, warning value is 2022-04-11.
For instance if validated end date is 2022-04-11, warning value is 2022-04-08
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.