ProjeQtOr free project management software - [SOLVED] Fraction of days for Activity duration - ProjeQtOr
 

[SOLVED] Fraction of days for Activity duration

More
02 Jun 2022 00:01 #1 by Marty
Hello people.
We're just starting to use PorjeQtor for the first time and as a Newbee user, I have my first Newbee question. And I did try to find the answer in the forum before I asked.  
Here it goes:
I'm putting together a project and assigning tasks.
I get into trouble when I try to enter a fraction of day for duration (ex: 0.5d or 0.25d),  I get blocked and an exclamation point warning. (see attached screenshot)
Is there an obvious reason for this like a setting or other rule that I did not find in the manual?

Thanks for your help.  I will be back with more, I'm shure. :-)
  
 
 
Attachments:

Please Log in or Create an account to join the conversation.

More
02 Jun 2022 09:37 #2 by Arkhanje
To plan for half a day, you can use the "Manual planning" or "regular between two dates for half a day" or "quarter of a day" planning modes.

But in any case, the planning will take into account the workload of the resource and not the duration.
The durations are in full days on the Gantt so even for 0.5 workload, 1 day will be indicated in the duration
The following user(s) said Thank You: Marty

Please Log in or Create an account to join the conversation.

More
02 Jun 2022 15:58 #3 by Marty
Thanks Arkhanje.
Can you suggest where I can find an explanation of Manual Planning or something that will help me understand the workflow concepts and options I have?  I'M searching the help files with no results.
I have also looked at many videos that don't cover an entire workflow. 
Thanks  
Martin

Please Log in or Create an account to join the conversation.

More
02 Jun 2022 21:00 #4 by Marty
Correct me if I'm wrong.
I realize that there is a difference between PROGRESS-Duration, and Ressource Assigned Work.
From what I understand,
Progress Duration is for planning the timescale of the project (Only in full days if entered directly) ,
Ressourced assigned work which is the actual planned work and cost of the work.(Can be fraction of days.)
Ex:
If I plan 1 day for an activity in the Progress duration field, The gantt chart will display 1 day,
Once you assign work to a resource like 0.5 day, the cost will be calculated using 0.5 day and not 1 day.
Thanks for your help.

Please Log in or Create an account to join the conversation.

More
03 Jun 2022 09:37 - 03 Jun 2022 09:43 #5 by Arkhanje

I'M searching the help files with no results.



Press F1 from ProjeQtOr...
Or go to the online manual accessible from the website here


 
Last edit: 03 Jun 2022 09:43 by Arkhanje.

Please Log in or Create an account to join the conversation.

More
03 Jun 2022 09:40 #6 by Arkhanje

Correct me if I'm wrong.
I realize there is a difference between PROGRESS-Duration and Resource Assigned Work.


absolutely

If I forecast 1 day for an activity in the Duration field, the Gantt chart will show 1 day,


once again, yes absolutely

Once you assign work to a resource as 0.5 days, the cost will be calculated using 0.5 days and not 1 day.


and yes !

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.073 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.