Hello,
We are trying to insert some of our previous projects into ProjeQtor and I'm having trouble with the start date.
We're doing this for reference purpose and also to have a track reccord of our developpement work.
When I insert a start date of January 1st 2021, the start date defaults to today's date.
Is there a way to force the system to accept Project structures (Project' Activities and expenses, etc) before the current date?
Thanks
I did some digging last night and I think I found a way to do this.
I changed the parameter : Do not start before validdated date to NO
Then I entered : IN PROGRESS date and DONE date.
This seems to give me the result I want.
My next step will be to import the Activities by EXCEL table in the same manner and I should have my archived project structure. I will also have to look at including the Assigned, real and left work for cost calculations.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.