View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Support us on Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Global Parameters - ProjeQtOr
 

[SOLVED] Global Parameters

More
02 Jul 2022 14:39 #1 by chandrashekhar
Hi Expert,

Need your assistance as we want to configure number of hours per day=9 instead of showing 8 under Unit for work in work time tab in Global Parameters .
We are using ProjeQtOr Version 9.5.5.
 
Attachments:

Please Log in or Create an account to join the conversation.

More
02 Jul 2022 15:22 #2 by babynus
Replied by babynus on topic Global Parameters
This is not possible (and should NOT be done) if some real work is entered.
Note that work is store in days, do display and input is done thanks to a convertion.
If you change 8h/day to 9h/day, resoures who entered 8h (1day), would now see 9h (which is not what they input)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.