Hi,
On a project in progress, I want to create a meeting to keep track of information discussed.
I allocate some people to this meeting with a 0.1 day for the work load. They are available this day
They cannot fill their timesheet with this task (the meeting line is not displayed) and Projeqtor says that this work is not planified.
What is wrong ? How can this meeting be available in the time sheet ?
A screenshot is available.
Many thanks for the feedback
The "purple" task means one of the resource cannot be planned on hte task.
You idenfy the resource with the read work displayd in assignment table.
The reason can be :
- the resource already recorded real work on the meeting date
- the resource is not on the project on the meeting date (look at start and end date of allocation to project)
- the resource is not present at all on the meeting date (look at start and end date of the resource)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.