Hello everyone,
I suppose a simple project with a PM and an architect for a specific sequence, "think".
I set a PM with 1FTE and 100% daily rate and this architect with 1FTE but 50% daily rate on this project.
I expect the planning to get longer because I affected only this ressource for my 20d sequence "think".
However, even if I check "automatic run plan" nothing appends on the planning.
I tried changing the Architect FTE to 50% independing to the project or I tried to change the rate regarding the "think" activity within the project but no consequence on the planning
your bars are pale green. This indicates that you have not assigned a workload to your resource. Look at your assignment table, it has 0 days assigned.
The validated workload that you enter does not affect your planning and recalculating the planning will not change this.
A short tour
here
will give you better information on dates, durations, work and costs
Hello Arkhanje,
You are so helpfull
I will test even if I believed I have tested it with a all green color but I should have made an error within this section PS : I will update this topic to solved with my feedback when I am gonna to test it
Actually Arkhanje was true so I began to play with the assignement.
Regards, Christophe
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.