26 Oct 2022 09:31 - 26 Oct 2022 09:32 #1 by Willowonline
time was created by Willowonline
Hello,

I don't understand where this limit comes from.
We have configured 8 hours of working hours per day, see PJ.

However, we are limited to 7.5 hours per day.
Is there another setting to change?

Thanking you for your help.



   
----

Bonjour,

je ne comprends pas d'où bien cette limite.
Nous avons configuré 8h d'heure de travail par jour, cf PJ.

Or nous sommes limités à 7.5h par jour.
Y-t-il un autre paramètre à modifier ?

En vous remerciant pour votre aide.
Attachments:
Last edit: 26 Oct 2022 09:32 by Willowonline.

Please Log in or Create an account to join the conversation.

More
26 Oct 2022 09:36 #2 by Arkhanje
Replied by Arkhanje on topic time
it is possible that you have set a limit directly on the resources screen.

 
Attachments:

Please Log in or Create an account to join the conversation.

More
26 Oct 2022 09:41 #3 by Willowonline
Replied by Willowonline on topic time
Thank you il will try.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.049 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.