Hi, we have such a problem and can't figure out what it stems from.
1. When planning is "as soon as possible" and run the calculation : OK
2.If change planning to "recurring (on weekly basis)" - 4h each Friday - and run the calculation : KO, assigned time is not properly calculated - validated is 8h, but automatically is assigned 80h and planned end date is 02/2024. Why is this difference? What we expect is these 8h to be allocated for 2 Fridays
Recurrent mode is a special mode planning each week, the same selected workload by day over a week, during the whole project. You can limit this beahavior by two milestones steering this activity beetween two dates.
it takes into consideration the valided workload to planified one day of workload over one opened day if it is the single information it gets. Otherwise it plans with workload given independltly of validated workload, that's happened using recurent mode.
This being said, how did you manage to provide real workload when there is no longer anyone assigned to the activity? Could i watch too the screen about your project please
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.