20 Dec 2023 17:27 #1 by pdecloedt
I have read two différents thinks in the help for order of calculation priority method.

first I read:
  1. Manual Planning
  2. Dependencies (Predecessor tasks are calculated first)
  3. Prioritized planning elements
  4. Project priority
  5. Task priority
  6. Project structure (WBS)

    Second I read:

    The calculations are performed task by task, according to the following organization:

    1- WBS
    2- The validated end date
    3- Priorities of activities
    4- Project priorities
    5- Planning modes
    6- Dependencies

    So what is the order high priority calcultation 

     

Please Log in or Create an account to join the conversation.

More
21 Dec 2023 09:27 #2 by alainforma
Replied by alainforma on topic calculation priority
Hi,

Could you tell me where do you find this kind of informations, which links are they coming from ?
The good answer is the first sort.
The following user(s) said Thank You: pdecloedt

Please Log in or Create an account to join the conversation.

More
21 Dec 2023 09:32 #3 by pdecloedt
Replied by pdecloedt on topic calculation priority
I find it on th helping menu on the application

Please Log in or Create an account to join the conversation.

More
21 Dec 2023 09:34 #4 by alainforma
Replied by alainforma on topic calculation priority
Thank you, but what about the second sort ?

Please Log in or Create an account to join the conversation.

More
21 Dec 2023 09:35 #5 by pdecloedt
Replied by pdecloedt on topic calculation priority
could you please explain me the third point ...

Prioritized planning elements

Please Log in or Create an account to join the conversation.

More
21 Dec 2023 09:39 #6 by alainforma
Replied by alainforma on topic calculation priority
modes of planification get an order of priorization beetween them.
Manual then regular then recurring then ASAP
The following user(s) said Thank You: pdecloedt

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.055 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.