When i look into planning or repport i dont realy understand how pool work cause in pool "montage", i've got 2 people
but in repport "disponibility" the pool seems 100% free !
i just do it for test and see that pool time is changing but contributor time is not moving ?
( they are only 2 on this pool .. ) so when i put 100h to pool it should impact availlibily of this two peoples ?
With 100% you mean that resource is fully available into this pool by day. Will she be planified on this task among resources of this pool, this day or another one, could be the real aim your are looking for...reading the Gantt once calculated or reports...
For your complete information, we would like to remind you that we are organizing a two half-day training course on February 14 and 15 to learn how to plan projects with Projeqtor. All conditions are on our site.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.