So i have some activities defined, and some users.
One activity shows 3700 hours, real work, for one user associated to it, but cannot find where exactly it is set.
So i go to the activity, select Progress, then on Assigment, i see the user, and it has real h 3700 .
How can i find from where it is comming from ?
Maybe in the tables ?
EDIT:
Seems it has something to do with initial planned and real start and end date. They are very big, and it seems that it take the hours per day and calculates that big hour value.
But i see i cannot change those fields.
Hmmm... i think i need to check the manual )
Indeed. The planned and real
dates
are automatically populated by the application. The planned date is based on the workload you have assigned to the resource and their availability, and the real date is manually populated via timesheet by the resource.
The real date indicates the date of the first assigment. This gives you the correct assignment week to check.
Right-clicking on a
bar
showing real work will give you details of the resource's work.
Validating allocations
can also be a good way to check data as well as certain reports on actual work.
You can't modify them directly, but you can use the control levers to adjust the planned dates and delete or modify timeheet for the real work.
So ive been looking around for quite some time and i just cannot figure out where those values are coming from.
I can see the value in the timesheet for this resource, on the "real" column, at the front, and also on the revised column.. But i dont know from what its actually calculated.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.