[SOLVED] priority planning activities

More
12 Dec 2025 09:28 #1 by pdecloedt
Hello, I have a scheduling question: When activities are under a parent activity, and the parent activity is scheduled between two dates, why don't the child activities in "as soon as possible" mode start from the validated start date of the parent activity?

Please Log in or Create an account to join the conversation.

More
12 Dec 2025 16:06 #2 by babynus
Sub-activities will never be planned from Parent .
The process it exactly the opposite : parent is planned from sub-activities.

You can notice that when an activity has sub-activities, it does not have a planning mode any more : its start / end dates are calculated from sub-items, and if it has some work it is leveled between these dates.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: pdecloedt

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.028 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.