Validated days per resource

More
27 May 2026 17:02 #1 by maitefournier
Hello,
Is it possible to split Validated days per Resource ? It seems only the Assigned days can be split. We would like to be able to monitor the Validated days per Resource (that are paid days) vs the Assigned days (that sometimes go above). How can we do that in Projeqtor ? Thank you

Please Log in or Create an account to join the conversation.

More
27 May 2026 19:35 #2 by babynus
Replied by babynus on topic Validated days per resource
Yes, Validated work is only defined on the Activitiy.
On the assignement you only have assigned real and left work (and also planned=real+left)

In your case you should just set Assigned as Validated, then update left work if some extra work is done.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.