1) When I have part-time resources I use "capacity (FTE):" 0.8: Planning is false (time is longer than reality)
If I put capacity (FTE) to 1 and assignment rate to 80% it's OK? Why capacity = 0.8 is different allocation rate = 80%
2) When I analyze the reports I have a difference between "work per avtivity synthesis" & "work yearly" why different calculation?
1) When I have part-time resources I use "capacity (FTE):" 0.8: Planning is false (time is longer than reality)
If I put capacity (FTE) to 1 and assignment rate to 80% it's OK? Why capacity = 0.8 is different allocation rate = 80%
Here are the differences : Resource Capacity = 0.8 : only 0.8 per day will be planned, whatever the tasks Project Affectation Rate = 0.8 : only 4 days per week will br planned on the project.
(so 1 day per week can be planned on another project, so resource is used at 100%) Activity Assignment Rate = 0.8 : only 0.8 per day will be planned on this task
(so 0.2 per day can be planned on another task)
2) When I analyze the reports I have a difference between "work per avtivity synthesis" & "work yearly" why different calculation?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.