Resource assignment from a date

More
05 Feb 2013 11:18 #1 by AcaUser
Hi,

First, congratulations for your work : your software is very good and very useful.

I have a question : how can I assign a new resource to a projet at a fixed date? (after the project has begun). For example : my project start the 15/01 but the resource is only available the 01/02.

Thanks for your answer.

Please Log in or Create an account to join the conversation.

More
05 Feb 2013 11:52 #2 by babynus
It is not possible yet. :oops:
This evolution is planned : Ticket #164. :woohoo:
.. but not considered urgent :angry:

You must manage differently.
For instance :
- put a contraint to firt activity of this recource :(
- manage all your projects with Project'Or RIA : this way the availability of all resources will fit reality ;)
- define some specific task (maybe on administrative projet) such as "Other Projects", and enter some real work for the resource for the unavailability period. B)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
05 Feb 2013 11:58 #3 by AcaUser
Thank you for your quick answer. :)
I will use one of the workaround you suggest...
but I vote for the ticket #164! ;)

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.