Hello, in my project the following situation occurs:
John works on Mondays and Thursdays from 6pm to 9pm.
Joe works on Tuesdays and Fridays from 7pm until 11pm.
Mary works on Saturdays and Sundays from 12am until 8apm.
How I can assign this calendar to each of them in order to assign them to control my activities and projects?
thank you very much
All you can define is :
- John has capacity of 3 hours a day (capacity = 0,375 for a 8 hour day)
- Joe has capacity of 4 hours a day (capacity = 0,5 for a 8 hour day)
- Mary has capacity of 8 hours a day (capacity = 1 for a 8 hour day)
Then affect each resource at a rate of 40%, to insure they work only 2 days a week.
Weekly work planning will be correct, but you won't be able fix days really planned for each.
Calendar per resource is an already identified evolution (Ticket #714), not really planned yet.
The ability to set the days and hours of work can make a real flexibility for the allocation and control of activities and projects. Otherwise, when teams are important, the manager must be a good mathematician ...
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.