14 Mar 2013 11:47 #1 by campsy
Hello,

Soon, we migrated from version 1.9 to 3.14. Great job for V3, there are plenty of interesting new activities for project management.

To reserve resources we have to implement a project to manage absences and holidays, we need to start calculating the schedule once a week in "automatic" mode.

I have wanted to know is it is possible to run a script or via a scheduled task on the calculation of the schedule on all projects? or is it necessarily must do manually?

Thank you in advance for your answer

Please Log in or Create an account to join the conversation.

More
14 Mar 2013 16:56 #2 by babynus

I have wanted to know is it is possible to run a script or via a scheduled task on the calculation of the schedule on all projects?

No

or is it necessarily must do manually?

Yes.
IMO, planing recalculation should always remain a manual activity. It is PL responsibility to check each time impact of new calculation.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.034 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.